How long does it take?
The honest answer is in calendar days, not production rates, because the thing that controls the schedule is drying time and nobody controls that. A single room repair is typically four days: hang and tape, coat, coat and sand, then texture or prime. A whole-house remodel is a day or two to hang and then four to six working days of finishing, more for a Level 5, more again in a cold or damp week. Setting compound can compress that; ready-mix cannot. Anyone promising a three-coat Level 4 in two days with ready-mix is either using hot mud or skipping a coat.
How do you handle dust in an occupied house?
Layered, and we will tell you which layers your job is getting. Poly and tape on floors and openings. Zip-wall containment with zipper doors at the work area. Sealed supply and return registers with the HVAC off or the return isolated — a running return pulls sanding dust into the ductwork and redistributes it through the house for months, and it is the step most crews skip. HEPA vacuum sanding at the source, which is slower than dry sanding and is the single most effective thing anyone can do in an occupied house. And a negative air machine with HEPA filtration exhausting outside, so air flows into the work area and never out of it. On a pre-1978 house, containment and HEPA are not a courtesy — the EPA lead rule requires them.
Why are the bids so different?
Almost always one of four things. A different finish level. A different board spec. Different inclusions — texture, priming, specialty trim, high ceilings, demolition and dump fees, containment, framing repair. Or a crew that is not carrying workers compensation and liability. The useful question to ask all three bidders is: which GA-214 level, on which surfaces, and are texture and priming in the number? If two bids answer that differently, they are not bids on the same job.
What is normally included and what is extra?
Normally included: board, fasteners, tape, compound, standard corner bead, and the labor to hang, tape, coat and sand to the specified level, plus cleanup of drywall debris. Normally extra, and this is where bids diverge: a finish level above the base, texture, specialty board, specialty trim like bullnose or reveals, ceilings over nine or ten feet and anything needing scaffold or a lift, framing repair, demolition and disposal, containment and negative air in an occupied house, priming, asbestos or lead testing, insulation, and extra mobilizations when we have to come back because another trade was not finished. We itemize those rather than bury them.
You quoted per square foot. Is that my house's square footage?
No, and this catches almost everybody. Drywall is measured in square feet of board, not square feet of floor. Once you count both faces of the interior walls, the ceilings, the closets and the garage, a house contains several times its floor area in board. So a per-square-foot price on drywall is not comparable to your home's listed square footage, and a homeowner dividing one by the other is comparing the wrong two numbers. Ask for the board quantity and the price will make sense.
Is a very low bid a problem?
Do the arithmetic rather than trusting an adjective. California publishes prevailing wage determinations for drywall installers and for drywall finishers in San Diego and Orange counties — they are public, they are current, and they tell you what a legally employed, insured drywall worker costs per hour in wages and benefits on a public job before the contractor has bought a single sheet of board or paid for a truck. Private residential is not public works and the numbers are not the same, but the floor is instructive. If a bid is half of everyone else's, something in that list is not in the price, and the two usual candidates are coats and insurance.
Do you fix the framing if it is bad?
We will, and we will tell you before we do, because it is not drywall scope. Crowned studs, missing backing, framing out of plane, headers not flush — those all become visible in the finished wall, so somebody has to deal with them. We price it as its own line and get it approved rather than absorbing it quietly, which just teaches everyone that it is free and leaves you thinking a wavy wall was a drywall problem.
Do you do repairs, or only whole jobs?
Both. A single patch in a hallway is a real job and it gets the same sequence as a whole house, just compressed: cut back to solid board and to framing where we can, back the patch properly, tape it with paper, coat it out wide, match the texture off an approved sample, and tell you honestly what the wall will need in paint afterward.
Will there be pops or cracks later?
Probably a few, and here is the honest version. New framing dries out over the first year and a handful of fastener pops is a normal consequence of that, not a defect. Hairline cracking at a door corner or a wall and ceiling junction in a new house is usually the building settling. What is not normal is a systematic pattern of pops, a crack that keeps coming back in the same place every winter, or joints that show up as bands after painting. Ask any contractor, us included, how first-year touch-up is handled, and get the answer in the contract before you sign rather than after something moves.